Ealing & West London College – Road, Parking & Paving
Client:
YJL
Value:
£148,000
Programme:
6 weeks completed April 2005
Description:
Predominantly a concrete block paving scheme with some bituminous surfacing and face brickwork and planters.
This was another scheme requiring a great deal of work to be carried out against a very tight programme. The handover date was crucial in order to coincide with the completion of the building works to the new block by YJL.
Again there was the need for out of hours working and close co-operation with the college and with other contractors involved in the project.
The result – once again, high quality work delivered on time.